Full Cable Containment Delivery for an 80MW Hyperscale Data Centre
Project Overview
We delivered a full cable containment package totalling 20,000 metres for an 80MW hyperscale data centre in the Nordics. The project was a first of it’s kind, next-generation data centre, requiring large scale logistics and precise coordination. In total, approximately 80 x 40ft trailers were delivered to site over the course of the programme.
Project Overview
To supply industry leading Magnelis external cable containment for modularised systems, alongside pre-galvanised containment for internal applications, meeting both performance and durability requirements for a high-specification data centre environment
Key Challenges
- Highly aggressive project programme
- Increased production speeds to meet client timelines
- Ongoing design changes requiring rapid response
- Complex logistics aligned to a pressurised construction schedule
Our Approach
We adopted a highly collaborative delivery model, maintaining continuous engagement with the wider project team. Regular coordination calls ensured alignment across material selection, procurement lead times, and site delivery schedules. This proactive approach allowed us to respond quickly to design changes while maintaining momentum across the programme.
Outcome
In partnership with RMS (manufacturer), BK successfully delivered the project in full. All materials were supplied on time, fully compliant with project specifications, and seamlessly integrated into the site programme. This eliminated potential delays and supported efficient, uninterrupted site execution on a landmark hyperscale data centre development.